Salt Fork Wind
Donley and Grey Counties, TX
- Avoids 510,000 metric tons of CO2 emissions annually – equivalent to 107,000 passenger vehicles driven
- Coordinated design of split ownership substation between transmission company and project.
- Implemented real time meteorological data into crane lift work using onsite towers.
- ERCOT/CREZ
SERVICES PROVIDED: Development and Construction Consulting / Professional Services
SIZE: 174 MW
LOCATION: Donley & Gray Counties
OPERATING SINCE: November 2016
UTILITY: Salesforce VPPA and The City of Garland
TURBINE EQUIPMENT: 87 V 100 2MW wind turbines
TRANSMISSION: ERCOT/CREZ
INTERCONNECT: 345KV
LAND: 35 landowners on 16,700 acres
CONTRACTOR: Blattner Energy
DEVELOPER: Cielo Wind Power
OWNER: Southern Company