Goat Mountain Wind Ranch®
Coke & Sterling Counties, TX
- Goat Mountain will be Edison Mission Group’s first wind project in the ERCOT market
- Goat Mountain is Edison Mission Group’s second wind project in Texas
- Edison Mission Group and Cielo Wind Power have jointly developed this site
SERVICES PROVIDED: Development and Construction Consulting / Professional Services
LOCATION: Coke & Sterling Counties, TX, approximately 30 miles north of San Angelo, TX
SIZE: 150 MW
COMMERCIAL OPERATIONS DATE:
PHASE 1: March 2008
PHASE 2: March 2009
TURBINE EQUIPMENT: 80 Mitsubishi MHI 1000A / 29 Mitsubishi MHI 2400 2.4 MW w
UTILITY: ERCOT (Electric Reliability Council of Texas) Retail Market
TRANSMISSION: 1-345 kV Substation, adjacent to 345 kV Interconnect Lines
INTERCONNECTION: 354 kV system of LCRA Transmission Service Corporation
LAND: 20 landowners
EPC CONTRACTOR: Wanzek Construction
DEVELOPER & MINORITY PARTNER: Cielo Wind Power
MAJORITY OWNER: Edison Mission Group (Irvine, CA)